The project, to be located at XXXX is to design and construct general office space and a laboratory building. The project will also demolish space to meet the one-for-one requirements. The threshold key performance parameters of the project are:
Description of Scope Threshold KPP Objective KPP
Facility Size Xx,xxxSF Xx ,xxx SF
Demolition Xx,xxxSF Xx ,xxx SF
LEED Certification Gold Platinum
Note: The threshold KPPs are the minimum parameters against which the project’s performance is measured when complete. At CD-2, the documented threshold KPPs comprise the official Performance Baseline.Objective KPPs are those additional parameters that will be added to the project if contingency is available.
The project is declared complete (CD-4 criteria) when the XX buildingis complete, has been commissioned, and is ready for beneficial occupancy.