I’m writing to summarize for our conversation via phone as follow;
1. Activity:
- Temporary use of 25 T Mobile crane for Mold lifting.
- While the installation of overhead crane is delayed and not yet completed.
2. Things to prepare:
- Critical lifting plan has to be prepared and submitted by KONE.
- Critical lifting plan has to be coordinated and approved by the safety of VALEO. (Under the organizing by KONE)
- Crane certificate has to be provided by KONE. (ปจ. 2)
- Rigger with certificate has to be provided by KONE.
- The said activity is under the cover of CAR providing by Umemura. (According to a contract condition Clause 7. Insurance, C
3. Date of activity:
- Initially as I checked with K. Duriyapong is 25-Sep-2015.
This is to make a clear understanding to all.