8-24 May’15 – Increase POB to 10 POB (2 Teams) to expedite insulation work
Dear K.Chanin,
Platong will have complex S/D during 15-26 May 2015. We need your team to remove/installed the insulation.
Detail document are attached for your cost estimation ,material lead time and work duration.
Please help send us the quotation and give me a call if you need more information
1st scope : Remove and Install insulation window of V-3930, Heat recovery expansion tank
• Remove insulation window for inspection and install back (might need to remove some insulation section and drill a new window for future inspection)
• See attachment for number of inspection window and detail of vessel
2nd scope : Remove and install insulation of the Hot gas bypass piping
• Remove the insulation of the old pipe
• Install new insulation with fabricated material + reused insulation from old pipe
• See attached for isometric drawing