Current:
Systems < 5 kW are currently automatically
approved, but this limit is under review.
Systems >5 kW require approval from asset
management to ensure that they are network
capacity sufficient.
Systems >30 kW are treated as large
connections and subject to a network load
flow study by a regional distribution
planning team and a protection study.
Proposed:
Guidelines for the application to install a
large PV system are under preparation to
streamline the process