In so far as practical and agreed by the Owner, Performance Tests may be carried out during achievement of Normal Operation Period. The Owner shall not be obliged to agree to Performance Tests being carried out during achievement of Normal Operation Period and any early Performance Tests shall not relieve the Supplier from any responsibility he has under the Contract