a. KCC advise Allied to study process of submittal.
b. KCC advise Allied to study how to provide work method statement for submit to VPL (If VPL request)
c. KCC advise to start exchange information from now, don’t wait for next 2 week as Allied planning to commence work.
d. Allied Metal inform shop drawing of Phase 1 almost done but only for BOH that not complicate, But for FA have to coordinate with ID work.
e. Detail of install top counter above Kitchen equipment to be concluded ASPA: Counter sit on Kitchen equipment or have counter support area by area.
f. Allied Metal has to advise service access or method if need for Kitchen equipment.