Once again, it doesn’t feel as though we have a lot of choice in the matter. We will end up air freighting parts. I think we need to sit down on Monday and discuss JW’s responsibility in all this. I am getting the feeling that we have never fully recovered from the quality issues.
Go for option 2. Alert JW that due to their inability to produce ontime, we are going to need to discuss further options to air ship. Very clearly, they are over a month behind committed lead times. We can’t anticipate or plan for issues like that. And it puts an unreasonable amount of stress on all of DSA.
I’m going to put through an order to airship in to try to get us some 2000-M and R0521’s, but we will most likely need more than that shortly.
Thanks,
Blake