To conclude we reject this value being taken off our account and request PPS to investigate fully with the tenant the extent of the damages which constitute this claim since no proper documentation or evidence has been provided and with the understanding from various parties that these works were in fact re-work due to the rejection of applications, again suggests that the blame and costs are not substantiated and should not be placed onto Permasteelisa