1-3 May’15 – 2 POB to Perform 2nd batch survey (Please confirm the duration per result of this survey)
3-7 May’15 – Increase POB to 5 POB (1 Team) to start installation work
8-24 May’15 – Increase POB to 10 POB (2 Teams) to expedite insulation work
24-29 May’15 – Drop 5 POB and complete all jobs on 29 May’15
Could you please help review the cost to re-submit the proposal for me in additional work required for this plan (More survey trips and Overtime jobs) to revise SR further
Many thanks for your support krub.