Here bellows are the status of Project:
Description Status Action by
- PPA 1
st submit: on July 15 Jinko
PEA rejected due to incomplete document
2
nd submit: on July 21 Jinko
- Public Hearing Finished on July 8, 2016 Egg Coop & Consultant
Remarks: Overdue, Jinko still didn’t pay cost of Public Hearing
Description Status Action by
- Building & Construction Permit Pending Jinko
- Industrial Works Permit/Factory Permit Pending Jinko
- Solar Power Plant Permit to ERC Pending Jinko
We hope Jinko can manage all permits in ERC’s Schedule with the right, quality and complete documents as the
Professional.