I got the newest information form SDS Mr.Ariie.
The contents are the following.
JATH's information as " the trial stage was finished" is correct.
But our products is going another way. Because the decision of specification is late.
Now conditions
First trial goods by die set for trial will be delivered on Jun.
JTEKT will take the checking and approve to trial goods.
JTEKT will inform the announcement for making die set for mass production on Jul.
SDS will deliver the mass production goods by die set for mass production on Oct.
Perhaps, JTEKT will approve to the mass production goods on Nov.
About some documents ( ex. PPAP, SDS )
The rule for making PPAP etc. in JTEKT.
The target : mass production goods.
Therefore, now, manufacturer can’t make PPAP and SDS. Perhaps, SDS and SITT will submit some documents on Nov.
If JATH have any question, JATH will ask JTEKT.