K. Kowit, as discuss in meeting yesterday Tentative Schedule shipment is,
2nd. Feb. 2014 Ship production deck extension panel no. 1,2 and 3 also Ship loose members.
9th. Feb. 2014 Ship Mezzanine deck extension panel no. 1,2 also Ship loose and Instrument tubing access walkway panel, angle post and Handrail etc.
Fabrication and coating tentative will be complete on 23 Jan 2014.Please:-
-Follow-up steel structure at yard #3 blast/paint still left behind send to yard #2 asap.(Plate 6mm 4’x8’ = 1 EA, FB6x100 = 10 EA sent to yard#2 already in today afternoon, for deck plate 8mm 5’x20’ = 12 EA are painting on going. We will send on Thursday(12-Dec-14).
Also pipe handrail socket Dia. 2” STD.(Already sent to yard#2 by today afternoon)
-Send pipe handrail Dia. 1 ½” to hot deep galvanized. Already sent to SSG to galvanizing in today morning and will be finished within 10 days so we will follow up.
-Order the angle bar and C-Channel for E&I support Ref. Dwg. S-0221. We already ordered in yesterday and will be arrived on Friday,13-dec-14 and to be blasted/painted primer before send to you on Monday(15-Dec-14).
-Check lifting gears Cert. for certify to re-used. To be informed.