Khun Weerasak,
That would be great help for Suzhou plant both line 2 and line 3.
Till today, trial test of line 2 goes well: Die and nozzles made in Suzhou Installation works well. Currently there are the following 3 aspects for line 2 running now:
1. Solid shaft had been delivered to site this later afternoon. That would be much easier for us to operating smooth rolls from Thailand.
2. Holes of Scrubber was shadowed by tray of pipes (see #151). Both you and Jim pointed this before. Contractors started modification and try to low down pipes last weekend. This work will be done in 1-2 days.
3. We find the painting of line 2 is peeling off from time to time, sometimes more serious as photos (#152-156) shown during production. --- I am afraid that it will bring negative impact on sales. If so, we intend to polish and repainting frames/beams above of smooth roll level, and We need your insight on this. Meanwhile, we enquired the time and quotation on this work. On the other side, we suggest we would not paint DRS line 3 in Rayong plant.
The other status for line 2 seems okay. We will try new solid shaft tomorrow.