17:56 P I M kaa
17:56 K.Lam one to K.Ka, one to k.Pim, one to k.golf
17:58 K.Lam i wont have time to do other things if i need to do that. also i dont have way to talk to k.golf about things like this. this is a group chat and k.golf (backend) is on this. please make sure he checks this group chat so requirements are not missed
18:01 K.Lam The project is very delayed already and if Chic Republic and Net Design don't work closely together, then the project will just keep delaying
18:02 K.Lam i think HTML is moving ok because me and k.pim here have a way to communicate closely and make changes
18:02 K.Lam but backend - if not work like HTML, will not move fast enough to deliver on schedule
18:05 K.Lam anyway, back to HTML na. i'll give K.Golf a call on Friday to see the status of backend (supposed to finish everything). anything else we can discuss in meeting on Monday 14:00