or utility systems, only solid grounding is recommended. The logic here
is that many distribution circuits extend through public areas and can be fairly
long, with taps, branches, and so on. Thus, although the line-to-ground fault at
the substation bus will be greater than the three-phase fault, this reverses
quickly, as the high-zero-sequence impedance soon becomes predominate