Due ITD have a plan to temporarily demolish the elevator and awning for protection the dust. Therefore, we will start to demolish on 15th December 2014 and schedule to finish on 23rd December 2014. However, ITD need to complete the street area, MET will accelerate to complete elevator work HS1, HS2 on 8th December 2014 and after ITD finish to demolish elevator, ITD need to handover this area to PISA for installation façade at this area for protection the water ingress to the building and handover work.