As checking and got validation from K.Saowaros, the 2 units is correct orientation per spec. But the remaining 9 units have inserted wrong orientation in a tube.
The wrong orientation 9 units are in partial tube which was inserted and issued from TCI and passed from QA buy off.
Have you checked and compared the units in a tube against logo on tube for your process?