Hi Nong,
Factory will only reschedule the ship date for PO.002/2015 & PO.007/2015 since the dates were due.
It will normally take around 2 weeks times from the date they receive the official LC.
The estimated ship date from Japan/MMD for these 2 orders will be around 27 Apr - 30 Apr if
we able to get the official LC before 13-Apr.
Scheduled ship date for PO.008/2016 is 21-Apr.
However, Ms Oh informed us that BTE want to add in items but we have yet to receive the revised PO from her.
Kindly refer email attached and assist to remind her on this.