ten daily discharge basis, depending upon the available data and
dependability studies there exist provision for its uprating [15].
Such investigations are valuable from refurbishment and uprating
point of view, because a century ago when project was commissioned,
no such studies could be undertaken because of inaccessibility
to site and lack of infrastructure at that point of time. Hence,
the details of the discharge as given in Table 1 are used to determine
the available power potential in the stream.