Dear P’A and Beer-san
For main portion of welding
1. Can hold CLP-U and can’t drop or loose when transpotation
2. Fix position for support Worker when assembly in NISSAN line production.
And for your question.
3. Welding what point, How many point welding?
- From current we’re welding CLP-U 2 point .So new CLP reduce to 1 point (refer picture as below)
Could you please select which point to welding by yourself (No.1,No.2 or No.3)
4. Tube diameter 54.0mm, Clip diameter 58.0 cannot fit with another part.
- For actually diameter of CLP-U we’re use CLP-U spec “ARS-M8-55” (D.55-58mm.) (Now not have sample to trial)
Engine M9T use PIPE-END D54.0 Expand to OD.57.0 mm.
Engine YD25 use PIPE-END D54.0 Expand to OD.54.2 mm.
Engine TR25 use PIPE-END D50.8 Expand to OD.54.0 mm.
Supplier (NORMA) send spec “ARS-M8-58” (D.61-64 mm.) (Supplier already have) to us and request to trial
so we can check only welding and appearance check If welding no problem (no crack , no loose)
I will confirm to them and then they will order spec “ARS-M8-55” to us and we will check assembly again.