13. FORCE MAJEURE
13.1 Neither Party shall be liable for any failure or delay in its performance under this Agreement as a consequence of causes which are beyond its reasonable control, including, limited to, acts of God, acts of civil or military authority, Fires, floods, earthquakes, riots, wars, sabotage, labor shortages or disputes, and governmental actions, provided that the delayed Party(i) promptly gives the order party written notice of such cause and (ii) uses its reasonable efforts to correct such failure or delay in its performance.