According to present weather forecast, it shows that there is high wind speed and high wave until 15 July’15.
For safety, team has decided to postpone relocation to 2nd week of Aug’15 (period to be confirmed later).
Because of expiration of PLE cer, it’s required NDT to support on MTI of all 48 pad-eyes at Porta Camp ka. And may also require FE welder in case of fixing ka. Pad-eyes details will be sent to you in separated e-mail ka.
Apologize everyone for the inconvenience may cause to you ka.