Following scheldule of CYCAM Van after we bought untill now.,
1.) Painting process will finish on Saturday 7 June that i will going to pick up on Sunday 8 June.
2.) Custom Rack process will start by L.O.R.D bike rack, a professional local bike rack company of Bangkok on Tuesday 9 June.
- Racks Processing is use 14 days.
- On Tuesday 9 june L.O.R.D is just measure inside of Van to start to make custom racks for CYCAM Van.
3.) Among racks processing in 14 days ,We can bring CYCAM Van to install Sticker design outside a Van.
- Sticker design is use 3-4 days to finish.
Noted.
- CYCAM Van will be ready around on Wednesday 24 June.