Dear Mr.Chote
Enclosed is our typical drawings for the bearing slab.
We send the drawing to you. Could you check it and give us your reasonable quotation of it ?
Construction Content as follow,
Construction Scope ,
1) km102~km126,exclude the brige. Total 22.8km
Detail Construction Content
1)Pile Head Cutting: cut square piles 0.8m and separate the DW (Rebar).
2) Sand layer construction: backfilling and compact the sand 100mm thick
3) Lean Concrete construction: pouring the lean concrete 50mm thick
4) Bearing Slab Construction:pouring the class B ( Clylinder 200kg/cm2) 300mm thick
CHEC Responsibility:
1) Provide hoad roads for IPEC
2)Provide construction place for IPEC
3)Provide drawings and specification to IPEC
4)Provide concrete and rebar (raw material) to IPEC
IPEC Resbonsiilibity
1) Provide electricity and water in the process of construction
2) Build the camp for fabricating the rebar, provide manpower and equipment to install the rebar
3) Provide manpower and equipment to pour the lean concrete and bearing slab concrete, include the concrete curing
4) In charge of the accomodation of the workers and stuff
5) In charge of the survey work include survery tools
Construction Schedul
1) Pile Cutting: No less than 150Nos/ per day
2) Bearing Slab: No less than 30m/ per day.
In according with our drawing and above information, please kindly give us your quotation as the unit price for the above work ( ??? Baht/ Nos. ????Baht/m3 etc )
If you have any questions, please contact with me directly.