Component 1 Partnership strengthening: There were difficulties in the management of LGUs
Component 2 Planning and policy development: The scope of works was not clear and the resource requirements were underestimated. Consultants were paid by person months, rather than deliverables, leading to problems in completion of outputs. Documentation of public policy consultations were not retained in all cases meaning that they may need to be repeated in order for policy approvals to move forward
Component 4 Use of Market-based Incentives: Expansion of EUF is dependent upon external factors; lack of COD standard in DAO 35 and delays in approval of GES by DENR may block implementation
Component 6 JSSTP: Change of procurement route led to some delays during the bidding stage. Minor delays were also caused due to increase in local counterpart funding and delays in possession of the site