Identifying the sensitivity of downstream activities is important in overlapping decisions. Starting a highly sensitive activity before all upstream information is complete entails an increased risk that significant rework will be required, thus eliminating some of the time savings due to the original overlapping. On the other hand, activities with a low sensitivity can be overlapped with little risk of rework required. By understanding activity sensitivities, project managers can make informed decisions on overlapping strategies.