Remind, if you don’t reply, I can’t release PO to you.
Thank you for your support if you have any question, don’t hesitate to contact me
Please reply commercial clarify and change data in quotation as comment.
- Validity change validity to cover PO issue within 7 Nov.16
- Contact change contact from K’ Prasit to Wanwisa
- Delivery Time: 1 weeks ARO (Inform job start and finish if this job completed.)
- Payment condition: 45 days by 100% completed job and submission of Final Documents (MDR).
- Delay Penalty: Applied for each shipment with 0.2% per day of total price and 10% limitation.
- Warranty Period: 12 months after commissioning.
- Document request: Test Cert.
Note** Reply within tomorrow before 10.00 am and support quotation R.0-R.1 also.
Thank you for your support. If you have any question, don’t hesitate to contact me.
Please sent more detail for us proceeding quotation. Because right now not enough
1. Specification for GIS and Transformer 115 kV and 22
2. Data Sheet of Cable
3. Splicing you installation Direct Bury of Above Ground