Dear all,
According to finally plan to install Robot End Cap Weld#3, 4 project at weld&test line1 on Nov 05 -13 '16. We plan to operate only End cap weld#1, 2 by using 1 way pass to robot leak check lane 1 or lane 2 by up to selected and we will shut down End cap weld#3, 4 is 1 week (5 working days) started from Nov 7 until 11 for robot & system installation. So I would like to invite all of you joint to discuss together for whatever of you are concerned about Robot End Cap Weld#3, 4 might be effected to the current process.