The deterministic model is based on the process chart with all characteristics shown in Figure 2 except for those listed in Table 2. All durations take on their most likely value and there are no quality failures (no rework). This model illustrates how the project progresses when everything in the system is certain, perfectly coordinated, and synchronized.