Dear Kh. Weerayoot,
As per our information the transformer was not yet ordered and it is not 100% clear who will be the agreed supplier. Following that we do not have final dimensions and weights and we are not able to finalize the foundation details.
Dear Kh. Chaiwat,
According to the above mentioned item could you please clarify the order status for the transformer. As per Behnam’s information the delivery time for a transformer is 4-6 months. Could you please crosscheck the same with the latest project schedule. Attached the one which you just sent us last week. According to that schedule the erection of the transformer shall start by end of March 2016.