8 Tender Breakdown
8.1 Conditions of Contract
• Our proposal is for a double pass pallet type freezer with end flow air circulation
• Hydraulic power pack is approximately 1.25 meters x 1.0 meters and is located adjacent to the tunnel.
• The tunnel functions will be controlled by an independent PLC located in our Switchboard.
8.2 Connection Points
• Conveyors – Start with our infeed elevating conveyor and finish at the 3 palletizing spurs
• Evaporators are standalone.
• Electrical installation terminates at our switch board, to be located adjacent.
8.3 Validity
• 30 days from date hereof.
8.3.1 Terms of Payment
1. A deposit of 30% of the contract price with order.
2. A further 65% in the form of monthly progress payments for equipment on site and off site, installation of, commissioning, engineering and any other works relating to the substantial completion of the Subcontract Scope of Works.
3. The final 5% on practical completion of the project.
4. Monthly progress payments will include variation sums for work and equipment on and off the site.
5. Other payment terms may be negotiated to suit.