2. Ten (10) per cent of the Contract Price of each Schedule will be paid against presentation of Drawing and Document Acceptance
Certificate to be issued by EGAT to certify the receipt of all drawings land documents required from the Contractor under Article 17.
Drawings and Documents to be Furnished by Contractor for such schedule, provided that payment shall not be made until EGAT has received
from the Contractor the statement or delivery order and appertaining documents giving evidence of delivery of the main equipment of that Schedule.
3. Ten (10) per cent of the Contract Price of each Schedule will be paid after the equipment have been installed, tested and operated
or used for a period of 30 calendar days and the acceptance of the said equipment has been made by EGAT against presentation of
Acceptance Certificate to be issued by EGAT and submission of maintenance security by the Contractor.
EGAT will list the minor pending claim(s), if any, and payment will be made by deducting such claimed amount.