The engagement team has identified an external resource to whom they would like to subcontract part of the work on a particular project. The manager preparing the BRET submission assumes that there will be a written contract with the subcontractor, but this has not yet been discussed with the partner in charge of the project. Two questions in the BRET form ask whether the contract includes the required independence representations and the termination clause. What should the manager do?