MC would like to inform NWRT about the CTO delay for the construction of D-14 foundation at the FGD area which was previously committed by NWRT to handover on 05-Sep-2016, but until this moment, the works are still on-going. Take note that the original CTO date for the L24 area including this D-14 was supposed to be on 20-Jul-2016 but due to NWRT’s default to provide more manpower to perform the work, the aforementioned area is almost of 2 months delay now.