Thanawat,
We would be glad to however we don’t know when your server room will be completed and ready for installations. Also, we need your Purchase Orders, POs, to schedule the subcontractors and order equipment. A number of products require that we make a deposit but we will not do this until we have your POs. Equipment with a lead time is listed on the quote.
The HP PC quote is going to expire tomorrow so please submit the PO for the PCs so we do not have to re-quote. PCs can be installed within 2 - 3 weeks of receipt at Aware using the process I described to you at our last meeting and referenced on the quote. Note this assumes your team has prepared all of the end-users and performs the data migrations. The last week of December is not included in the estimate due to the New Year holidays.
Please confirm the date that all work for the server room will be complete. We need the following complete in order to schedule Data Center work.
- Tile flooring
- All walls installed (windows can be done later)
- Doors installed
- Painting completed
- Roof and ceiling completed
We do not want to perform any of the installation work before the room is complete due to possible damage to equipment.
Thanks,
Adam
l