The inspector:
-Has to check that the correct drawing and other documents needed, with the correct issue, are used with the first article inspection.
-Has to check that all required measuring and test equipment is calibrated.
-Inspect the produced parts on the following criteria
Dimension
Cosmetic
Execution of applicable work instruction
Specifications on the drawing
-Sign off and stamp the FAI sheet(QR038) with the assigned engineer when the engineer FAI is requested.
-When the parts meet the above mentioned criteria, NCR is required refer to PM08 non-conforming item control procedure.
In case of it is a non-conformance from production and after correcting the product, the inspector has to create a new FAI sheet copying the former FAI sheet, except for the FAI Form issue