Dear Rena / Lyndia ,
PAT tested machine OK & handover.
Following are PAT after handover machine request : ( Please co-ordinate with m/s Rena of TCI )
1) Spare part supply : See attached copy. Part no. : 923855.1183
We have supplied 40 pcs : 20 pcs with blue colour & 20 pcs with Orange colour ( different supplier )
PAT can’t accept the Orange colour filter. They want all 40 pcs with blue colour supplier.
Under tender clause 4. Specification.
2) Under tender clause : 4.18 PAINTING
Sub-clause : 4.18.4 : Two layers of anti-corrosive paint & two layers of gloss paint to be applied to all parts.
( require factory certificate or confirmation letter )
3) Tender clause items unable to test in the field due to no facility at PAT site area. PAT require ISO certificate or letter of confirmation from factory.
4.2.2: lifting load weight not less than 7 metric tons from ground level and in the same time control boom extension until end stop ( stack 5 height containers) time not over 70 sec.
(No facility & no 7 metric tons container at PAT site, unable to test ). PAT require a confirmation letter from factory mentioned that this machine can comply
4.2.4: Driving speed (un-laden) not less than 25 km/hr.
Due to traffic & road condition at PAT site. Unable to test. Require factory certificate to confirm.
Attached is model : DCF100-45E8 : Lyndia can you get one copy of DRF100-54S6 from factory. This scan certificate report show this machine can run more than 25 km.hr.
4.2.5: Gradeability (un-laden) min 25% and with lifting rated load not less than 7 metric tons not less than 20%
( no facility to test at PAT site ) Require factory certificate to confirm.
Note : attached is the DRF100 sale specification. can you attached the latest copy of the sale specification
Rgds
Bernard Liu