Implementing the RFMEA Method
Project A
The original risk registers for Projects A and B are shown in Tables 2 and 3, respectively. The risks identified in Project A fell into four main categories, namely, Risk Project (RP), Risk Design (RD), Risk Manufacture (RM) and Risk