Dear sir,
Please be advised of our activities to date, details are shown below:
Tool box meeting began with physical exercise lead by VPE Safety Officer [Komsan K.].
a. Topic Discussion : Parking Area is not the repose or rest area. Please avoid to do so.
b. Lifting and proper barricade.
After tool box, each team group gathered together and conduct pre-job meeting for better understanding on their daily task assignment.
MES Activities :
Furnace A : Insulation Work is being demonstrated to MES Concerned persons.
Furnace B : Reinstatement work and Hydro test on Steam Tracing preparation are being carried out.
Furnace C : Steam tracing installation, Flushing FG VOC Line and welding connection joint with burner are being carried out.
Furnace D : Steam tracing installation is being carried on.
Furnace E & F : Fit up and welding FG Line and Pipe support installation are being carried out.
Furnace G & H : Set alignment Header FG Line, pipe support installation and welding header FG Line are being carried out.
MPR : MPR-A1 : Paint refurbish is being carried on. MPR-A2 : Pre-assembly column and Girder [S4-S5] are being carried on.
: MPR-B1 : Finishing work is being carried on.
: MPR-C1 : Welding work is being prepared.
: MPR-D1 : Scaffolding installation is being carried out for alignment work.
TLE Activities :
Furnace AF-01 : Insert Transfer Line Header is being carried out.
Furnace BF-01 : Modifying scaffold for insert transfer line is being carried out.
Furnace CF-01 : TLE Guide support Bolts are being installed.
Furnace DF-01 : Insert TLE Westside is being carried out.
Manpower : Direct is 130 persons and Indirect is 22 persons.
Note : Job done safely.
: Snake found at EM Meeting Room and Informed VPE For proper action.