ear,
After discussion with several parties include K.Nontaphon and K.Mala, I’d like to conclude that this work doesn’t require MOC due to the following justifications:
- “MOC F&O is applicable for hydrocarbon processing facilities and building which adjacent to hydrocarbon process. This case is considered out of MOC F&O scope. However I would recommend our ISA provide appropriate on engineering review on modification may have.” (quote from K. Nontaphon)
- Change scope is straight forward and not required complicated engineering detail.
ISA team (K.Sarote) will provide technical consultation including review and approval (via email) while execution could be managed by Settapat Maint Team further.
Thanks/Rgds,
Teeroj S.