Dear all,
Please inform all the contractors to allow in their quotations:
1) Construction electricity and water charges of their usage shall be paid by them. Contractor shall include temporary meter and connection themselves
2) HHT will provide free land for their construction of labour camp. Contractor shall include their own labour camp plus water / electricity and rubbish cleaning charges
3) HHT may provide labour camp room for contractor’s rental, subject to HHT ‘s decision at later stage
4) Worker shall wear tidy uniform and safety hats in the working areas, following HHT’s safety rule.
5) Worker shall be transported to and fro the working area by truck only. No worker cannot walk or wonder at Thana City golf club area.
6) Working hour shall be 8am to 6pm. In general no night work is allowed. Overtime work can be applied subject to approval. Materials in/out or loading/unloading which may affect the guest of TNC golf club will not be allowed. Delivery can be in night time after 11pm upon prior request and approval.
7) Temporary fence or covered walkway will be provided by HHT as per our planning drawings. Extra fencing and walkway or modifications of the existing fence or walkway, if required by the contractor, shall be at the cost of the contractor.
8) Contractor shall be responsible for cleaning and clearing their own rubbish on a daily basis, unless otherwise allowed by HHT.
9) Noisy or dusty work shall be requested and approved before proceeding.
10) No smoking is allowed.
11) Preparation of shop drawings and submission of samples if required (especially for ID and M&E work)
I will draft the scopes and conditions of work for each package for your sending to the contractor later