2.1.9 Delivering to Client a list of required spare parts, construction and commissioning spare parts and 2-year recommended spare parts (optional) within twelve (12) months from the Effective Date.
All spare parts required for Preakasamai Waste to Energy except 2-year recommended spare parts (optional) shall be shipped with the main equipment to which they belong in accordance with provisions stipulated in Appendix 1 Section 5.2.
If spare parts cannot be shipped with the main Equipment for which they are required, the Seller shall ensure that all spares are shipped in time to have them available at Site and checked into the stores at least (2) two months before the equipment to which they belong is put into initial service.
The optional recommended spare parts (if being placed order partly or wholly by Client) shall be shipped within the date(s) as agreed at the time of order.
2.1.10 Providing Construction Temporary Facilities at the Site of Preakasamai Waste to Energy Project such as temporary offices and sanitary facilities for the Seller.