This section shows how the information obtained from the calculations in Section 6.5.2 can be used to develop the time schedule. We recognize that for an activity (i, j), q represents the earliest start time, and 1j represents the latest completion lime. This means that the interval (O;,1j ) delineates the (maximum) span during which activity (i, j) may be scheduled without delaying the entire project.