Acceptance Test
When the installation, all clean-up work, adjustment and individual equipment tests have
been fulfilled, the Contractor shall perform the field test and commissioning of the
equipment, at his own expense, to the satisfaction and in the presence of MEA's
Acceptance Committee.
SECTION 3: GENERAL CONDITIONS (e-Auction)
Mar, 2014
If tests show that the requirements or guarantees have not been met, the Contractor shall
at own expense, make all necessary corrections. Additional tests shall then be made to
demonstrate to MEA's satisfaction the effectiveness of these corrections.
All expenses incurred by labour cost and equipment necessary for the tests and additional
test shall be for the Contractor's account.