- Before the kybt think price FF & RCU of spare part equals the price SOP. But now KYBT will get
charged more for a spare part for the FF & RCU
- Mr.Santi TSM informed that the support package. Let just add overhead. But may increase as true.
And in the part of parts inside the kybt add operations and 20% asked to consider decreased.
- Ms.Amornrat explain that the added cost of internal parts, but not 20%.
Mr.Iguchi tsm request clarification of the details of the operation of the internal parts.
- Mr.Iguchi TSM request KYBT clear details clearly. How much you want to charge and
Let TSM know it will be considered again. You need to consult with the spare part.
- Mr.Iguchi TSM informed that the ship parts spare part if last lot SOP, can adjust the price.
- For back order also problem that price. Mr.Iguchi inform kybt need to sent back order to tsm,
If not to assume wrong contracts traded.
- Mr.Santi TSM asked the kybt delivery using price SOP after agreeing about the price now to do debit note
increase or credit note, later.
- Ms.Amornrat reported on April, KYBT the send part to, by delivery note but has not issued invoice,
So ask the tsm helped to open a new PO.
- Mr.santi TSM informed that a letter asking to clarify details and will proceed to.
- Mr.Iguchi asked the KYBT to discuss about the price and back order again.
- Mr.Iguchi says, domestic FW xc-604 the kybt production next year's normal production.
Ask the KYBT help support too.