The new job distribution for both the operators is presented in Table 5. With this new work distribution, work elements F10, G1, and G4 are eliminated. In determining the cycle times for Operators 6 and 7 , it was assumed that increasing the number of operator in a job originally carried out by one operator to two operators will decrease the process time by half.