Pls revise the loading date because some of the COO form still not yet approve from our Cambodia custom and we able to load only one shipment on the 3rd Dec the rest is delay.
Pls see the red mark.
- 1 x 40’ HQ (inv.no.277614) , we have plan load on 2/12/13 Delay to load on 6th Dec, as Form D still not yet approve.
- 1 x 40’ HQ (inv.no.273782) , we have plan load on 3/12/13 Confirm load as planned
- 1 x 40’ HQ (inv.no.277577) , we have plan load on 6/12/13 Delay to load on 7th Dec, as form D still not yet approve.
Pls note : just let you know the cause of this delay due you late release us the invoice and packing list expecially form D, because I always notice you the inv & P/L must send us 2 week don’t wait for your production confirm the loading date. You can send us the invoice and packing list fist and we adjust the loading later.