3.1 Project originators shall follow EHs review procedure, as described in EHs Procedure VETL-EHS-P4.3.1.3 (EHS Review of Projects), which identifies any legal requirements for wastewater discharge if applicable.
3.2 All production and non-production wastes shall be characterized and managed properly as described in Environmental Procedure VETL-EHS-P4.4.6.5 (Waste Management Control).
3.3 Liquid and solid wastes shall not be discharged to the sanitary or storm sewer. A list of wastes generated by VETL can be found in the facility waste management program described in EH Procedure VETL-EHS-P4.4.6.5 (Waste Management Control).
3.4 All relevant EH procedures and work instructions shall be followed for specific liquid and solid waste disposal to prevent pollution of surface water and ground water.
3.5 Managed Materials shall be approved for use as specified in VETL-EHS-P4.4.6.2 Material Management. Only VETL-approved chemicals shall be used in the cooling water system discharges.
3.6 All bulk storage facilities and containment structures shall be installed, maintained and inspected to ensure the protection of the storm and sanitary sewers.
3.7 An emergency response plan shall be prepared and maintained to deal with major spill incidents in accordance with EH Procedure VETL-EHS-P4.4.7 (Emergency Preparedness and Response).