This project was selected during Round
III of DOE’s CCT Program. In October
1990 Energy and Environmental Research
Corporation (EER) signed an agreement with
DOE to conduct this project. Gas reburning
coupled with low-NOx burners (GR-LNB)
was tested at Public Service Company of
Colorado’s (PSCo) 158-MWe (net) wallfired
Cherokee Unit 3 near Denver, Colorado.
PSCo served as co-funder and host.
EER and Foster Wheeler Energy Corporation
were the technology suppliers, and
testing was conducted by EER. Additional
team members and co-funders were the
Gas Research Institute (GRI), Colorado
Interstate Gas Company, and EPRI. DOE
provided 50% of the total project cost of
$17.8 million.