Our two Supervision Engineers are continuously at site for providing guidance towards the job. Myself was at site till 16th instant and monitored the job progress very minutely & continuously. As per our understanding of the subject & requirement of the ESP at present state, it is very much difficult to complete the job within 22nd instant even after increasing of man power. Along with that, adequate resources will also have to be increased and more time per day shall have to be devoted.
More importantly, please note that the rectification jobs should be done only as per guidance & satisfaction of our Supervision Engineers (Mr. Deepak & Mr. Bikash) to get the best result without which, grossly job completion is meaningless